The Analysis of Time Acceleration and Productivity of New Shipbuilding Project
DOI:
https://doi.org/10.54324/j.mtl.v13i3.2125Keywords:
critical chain project management, scheduling, productivity, new ship buildingAbstract
This study aims to develop a project schedule for the X1 tugboat construction at PT XYZ using the Critical Chain Project Management (CCPM) method to accelerate completion time, improve labor productivity, and evaluate changes in direct labor costs. The direct observation and interviews were conducted to collect data on the work breakdown structure, activity durations, work volume, workforce size, and daily wages. This study applies Critical Chain Project Management (CCPM) to the X1 tugboat construction project at logistic and shipping company to develop a faster schedule, improve labor productivity, and evaluate direct labor costs. CCPM reduces safety time and centralizes the resulting buffer at the project level. With safety time reduced by 50%, the proposed schedule shortens project duration by 39.35%, increases productivity from 1 to 2/ Mondays, and increases direct labor costs by 0.14%.References
Abdurrasyid, A., Luqman, L., Haris, A., & Indrianto, I. (2019). Implementasi metode PERT dan CPM pada sistem informasi manajemen proyek pembangunan kapal. Khazanah Informatika: Jurnal Ilmu Komputer Dan Informatika, 5(1), 28–36.
Amalia Putri, F., Nugraha, I., & Veteran Jawa Timur, N. (2024). Optimizing Project Duration and Cost of Support Ship through Time-Cost Trade-Off Analysis and Microsoft Project Application: A Case Study at PT XYZ. 21(2), 173–186.
Aulady, M. F. N., & Orleans, C. (2016). Perbandingan Durasi Waktu Proyek Konstruksi AntaraMetode CriticalPathMethod (CPM) dengan Metode Critical Chain Project Management (Studi Kasus: Proyek Pembangunan Apartamen Menara Rungkut). Jurnal Iptek, 20(1), 13–24.
Bahnas, N., Adel, K., Khallaf, R., & Elhakeem, A. (2024). Monitoring and controlling engineering projects with blockchain-based critical chain project management. Automation in Construction, 165, 1–23.
Bahtiar, M. H., Santosa, A. W. B., & Trimulyono, A. (2023). Implementasi Metode Critical Chain Project Management (CCPM) Pada Proses Reschedule Kapal TB. Anugrah Lestari 02 dan BG. Alika 102. Jurnal Teknik Perkapalan, 11(3), 48–55.
Diswantoro, G. P. (2024). Analisis Optimalisasi Jadwal dengan menggunakan Critical Path Method (CPM) pada Proyek Pembangunan Kapal Tugboat 156, 67 DWT. Jurnal Teknik Perkapalan, 12(1).
Ersaputra, T. F., Amiruddin, W., & Santosa, A. W. (2022). Analisa Penjadwalan Proyek Pembangunan Kapal Wisata Glass Bottom Trimaran Pada Konstruksi Hull Dengan Precedence Diagram Method (PDM) Dan Project Evaluation Review Technique (PERT). Jurnal Teknik Perkapalan, 11(1), 14–22.
Fahmi, S., Mulyatno, I. P., & Zakki, A. F. (2023). Penerapan Critical Chain Project Management (CCPM) dalam Percepatan Proyek Reparasi KT. Selat Legundi II–206 dengan Variasi Pemotongan Safety Time. Jurnal Teknik Perkapalan, 11(4).
Faiizuddaroini, M., Nugroho, W., Supriyadi, S., & Nalhadi, A. (2022). Perencanaan Proyek Struktur Semi Gantry Crane Menggunakan Critical Chain Project Management. Operations Excellence: Journal of Applied Industrial Engineering, 14(2), 142–152.
Firmansyah, M. R., & Djafar, W. (2018). Tantangan Dalam Implementasi Model Integrasi Industri Perkapalan Di Indonesia. Jurnal Teknik Industri, 19(1), 28–37.
Istiqomah, M. R. M., Mulyatno, I. P., Sisworo, S. J., Hadi, E. S., Kiryanto, K., & Mursid, O. (2021). Penjadwalan Ulang Kapal Reparasi TB. Patra Tunda 3001 dengan Metode Jalur Kritis. Jurnal Teknologi Perikanan Dan Kelautan, 12(2), 161–174.
Musfar, R. F., Manik, P., & Tuswan, T. (2023). Analisis Percepatan Waktu dan Produktivitas pada Proyek Reparasi Kapal KM Dharma Rucitra VII dengan Metode Critical Chain Project Management (CCPM). Jurnal Teknik Perkapalan, 11(4).
Oktariansyah, O., Emilda, E., & Saputra, D. (2022). Pengaruh Biaya Bahan Baku, Biaya Overhead Pabrik Dan Biaya Tenaga Kerja Langsung Terhadap Penjualan Pada Subsektor Rokok Yang Terdaftar Di Bursa Efek Indonesia. Jurnal Media Akuntansi (Mediasi), 5(1), 89–100.
Pratama, A. P. (2023). FAKTOR-FAKTOR YANG BERPENGARUH TERHADAP KEBERHASILAN PROYEK PEMBANGUNAN UNDERPASS BULAK KAPAL. Sistem Infrastruktur Teknik Sipil (SIMTEKS), 3(1), 104–118.
Riyadi, M. (2018). Kajian Efesiensi Proses Produksi Kapal dengan Pendekatan Konsep Manufacturing Cycle Effectiveness (MCE) Studi Kasus PT. PAL. Wave, 9(2), 57–64.
Rizcola, R., Budiarto, U., & Yudo, H. (2019). Studi kasus keterlambatan proyek kapal bangunan baru Kapal Perintis type 1200 GT berbasis manajemen risiko di PT. JMI. Jurnal Teknik Perkapalan, 8(1), 31–37.
Siregar, N. S., Siregar, N. S. I., Artila, T., & Hasibuan, A. (2025). Hubungan Antara Budaya K3 dengan Produktivitas Tenaga Kerja di Sektor Konstruksi. JPEMAS: Jurnal Pengabdian Kepada Masyarakat, 3(2), 182–189
.
Soeharto, I. (1999). Manajemen Proyek (Dari Konseptual Sampai Operasional) (2nd ed., Vol. 1).Jakarta: Erlangga.
Sreenivas Padala, S. P., Divakar, L., & Vijay Kumar, P. (2023). Buffer Sizing in Construction Scheduling Using Critical Chain Project Management. Lecture Notes in Civil Engineering, 277, 969–978.
Sudarminto, T. A., & Mulyatno, I. P. (2020). Implementasi Perbandingan Critical Chain Project Management dengan Critical Path Method Repowering Kapal MV. Sinar Ambon. Jurnal Teknik Perkapalan, 8(2), 222–230.
Sugiyanto. (2021). Manajemen Proyek Rantai Kritis (1st ed.). Surabaya: Cipta Media Nusantara.
Sugiyanto, S., & Insan, K. (2022). Penerepan Optimalisasi Metode Critical Chain Project Management Pada Pelaksanaan Proyek Kontruksi. Rang Teknik Journal, 5(2), 352–363.
Suwasono, B., Baroroh, I., & Azhar, A. (2024). Analisis Biaya Industri Perkapalan. Surabaya: Hangtuah University Press.
Tamalika, T., Maryadi, D., Azhari, A., Pramona, Y., & Ardaisi, M. (2024). Implementation of the Critical Chain Project Management (CCPM) Model for Improving Time and Cost in a Project for House Type 36. Studi Ilmu Manajemen Dan Organisasi, 5(2), 357–369.
Tarigan, I. A. (2019). Analisis Perencanaan Proyek Pada Pembangunan Kapal Pandu Srikandi 003. Surabaya: Insititut Teknologi Sepuluh November.
Wahyuni, H. C. (2017). Analisa Produktivitas (Konsep Dasar & Teknik Pengukuran Produktivitas). Sidoarjo: UMSIDA Press.
Xiaoyang, W., Hamid, R. A., Hashim, N. A., & Osman, L. H. (2024). Research on the Importance of Project Pisk Management to Project Success. In Journal of Information Systems Engineering and Management (Vol. 2025, Issue 33s).
Downloads
Published
How to Cite
Issue
Section
License
Copyright (c) 2026 Ardian Syahputra, Wazirotus Sakinah, Pratama Yuli Arianto

This work is licensed under a Creative Commons Attribution-NonCommercial 4.0 International License.